PT Basic Energi Solusi’s Well BES-02 Completes Wire Logging

December 6, 2014

fabianPT Basic Energi Solusi (PT BES), a subsidiary of Basic Energy Corporation (PSE: BSC) reported that as of December 4, 2014, Well BES-02 has completed Wire logging. Production casings are presently being installed. Afterwhich, production testing will be conducted.

Well BES-06 is in the first phase production testing. Well BES-03 has completed production testing. Data from the testing is presently being analyzed and will determine the optimum parameters to be used during regular production.

Incidental Production during the testing period amounted to 56, 233 liters of oil, 45,410 liters of which have already been delivered to the local cooperatives as per contract terms.

Equipment for Well BES-04 and BES-05 are now being procured for use in production testing and regular production.

Source: http://www.fabian.ph/2014/12/pt-basic-energi-solusis-well-bes-02-completes-wire-logging/

Latest News

Basic Energy breaks ground on 43.41-MW Cadiz solar project

BASIC ENERGY Corp. has started development of a 43.41-megawatt (MW) solar power project in Cadiz City, Negros Occidental, as part of its 187.23-megawatt-peak (MWp) solar portfolio. In a statement issued on Wednesday, the listed company said its wholly owned subsidiary Basic Energy Cadiz 1 Corp. held the groundbreaking for the Cadiz 1 Solar Power Plant…

read more

ACMobility Sets Up Chargers Supporting Public Transport

MANILA, Philippines — ACMobility has expanded its electric vehicle infrastructure initiatives to strengthen public transportation networks through dual partnerships with Basic Energy Corporation and Grab Philippines. The Ayala Group’s mobility unit is deploying physical charging stations along major traffic corridors while launching digital fleet management technology to support electric buses, taxis, and ride-hailing vehicles. Through…

read more
View All Events